ARRA GRANT FUNDS

The goals and objectives of Weld County’s Energy Efficiency and Conservation Strategy are to invest Energy Efficiency and Conservation Block Grant (EECBG) funds in projects that yield proven energy results.  We have developed a multi-component approach to carry this effort forward.  Weld County’s EECHB goals and objectives will focus on the following areas:

-  Reinvest and maintain our capital facilities through energy enhancement /efficiency as warranted.

-  Hallmark the preservation and energy enhancement of our structures.

-  Increase the delivery of transit through increased use of technology by coordination of route trips and trip mapping; thereby reducing air pollution, transit congestion and greenhouse gases.

-  Provide our employees with technological support to enhance productivity, while reducing reliance on high energy consumptive practices.

-  Provide education and services to Weld County citizens through the use  of  E-Gov activities and the Internet.

PROPOSED ARRA PURCHASES

ARRA PERFORMANCE GOALS

LIGHTING COMPONENT

RECEIVE GRANT FUNDING - AUGUST 2009
BID PROJECT OUT - DEC 2009
#B0900170 - LIGHTING UPGRADE **BID AWARDED**
AWARD BID - JANUARY 2010
START CONSTRUCTION - FEBRUARY 2010
PROJECT COMPLETION - APRIL 2010

TRANSIT COMPONENT

RECEIVE GRANT FUNDING - AUGUST 2009
BID PROJECT OUT - JANUARY 2010 **ACS DID THE BIDDING ON THIS**
BID TABULATION/AWARD 3/19/10
AWARD BID - MARCH 2010
IMPLEMENT PROGRAM - MARCH - JUNE 2010
OPERATE WITH NEW SYSTEM - AUGUST 2010

HVAC CONTROLS UPGRADE

RECEIVE GRANT FUNDING - AUGUST 2009
BID PROJECT OUT - FEBRUARY 2010
BID TABULATION - HVAC CONTROLS
APPROVAL LETTER - HVAC CONTROLS
AWARD BID - MARCH 2010

BOILER - JAIL

RECEIVE GRANT FUNDING - AUGUST 2009
BID TABULATION - BOILER - WELD JAIL
APPROVAL LETTER - BOILER/WELD JAIL
BID AWARD DATE - 5/10/2010
PROJECT START DATE - MAY 2010
PROJECT COMPLETION - JULY 2010

BOILER - CENTENNIAL CENTER

RECEIVE GRANT FUNDING - AUGUST 2009
BID TABULATION - BOILER - CENTENNIAL CENTER
APPROVAL LETTER - BOILER/CENTENNIAL CENTER
BID AWARD BID - 5/17/2010
PROJECT START DATE - MAY 2010
PROJECT COMPLETION - JULY 2010